WTI are experts in planning, building and operating waste-to-energy (WTE) facilities. Their expertise is proven by their 45-year track record of providing reliable, WTE services to hundreds of customers in the US and UK. Their technology reduces carbon emissions by offsetting the need for energy from fossil fuel sources and reduces dependence on landfills.
In July 2020, Wheelabrator put into operation a new WTE facility at Kemsley in Kent, England. This facility is a combined heat and power 80MVA plant and will generate up to 49.9MW (gross) / 44MW (net) of sustainable, baseload electricity to power U.K. homes and businesses. The facility will process up to 606,000 tons (550,000 tonnes) of non-recyclable waste from across Kent and the South East.
Power plants ultimately need to be connected to a load. In the case of the Kemsley plant, waste that would otherwise have been sent to a landfill is processed and then exported to the National Grid transmission network. Renewable steam is also directly supplied to the adjacent paper mill.
WTI are clearly masters of their WTE domain but they recognized their need for electrical grid connection experience and specialist engineering expertise to efficiently connect their power to the greater grid. They needed a trusted Owner’s Engineer to support them through the entire project which they found in PSC.
PSC acted as WTI’s Owner’s Engineer providing electric system connection technical and regulatory support from the initial concept through the design and construction phases. PSC provided the following services:
PSC continues to provide ongoing technical guidance and support to the WTI engineering team through the commissioning phases.
WTI have benefitted from PSC’s consistent technical support via a single unchanging point of contact throughout all phases of the project. PSC’s experienced engineers provided a deep and necessary understanding of the UK electrical power system and requirements for their new generation facility. PSC services included providing support to the onsite team and ensuring the EPC’s design and installation met the specification and expectations of WTI. In addition, significant milestones were scheduled to occur during the COVID-19 lockdown. PSC seamlessly adapted to fully remote support while travel restrictions were in place, allowing for the project to progress relatively uninterrupted.